NO.1 Which type of team can be defined as a group of people with a shared goal who fulfill their
roles although spending little or no time meeting face to face?
A. Co-location team
B. Virtual team
C. Consultant team
D. Departmental team
Answer: B


NO.2 Which tool or technique allows a large number of ideas to be classified into groups for review
and analysis?
A. Idea/mind mapping
B. Affinity diagram
C. Brainstorming
D. Nominal group technique
Answer: B

PMP再テスト   PMPオンライン   

NO.3 A method of obtaining early feedback on requirements by providing a working model of the
expected product before actually building is known as:
A. Brainstorming.
B. Benchmarking.
C. Context diagrams.
D. Prototyping.
Answer: D

PMP教材   PMP受験方法   

NO.4 Which of the following schedule network analysis techniques is applied when a critical path
method calculation has been completed and resources availability is critical?
A. Resource planning
B. Applying calendars
C. Resource leveling
D. Resource conflict management
Answer: C